Can we talk about the 28 day strength rule? A lab tech in Toledo set me straight on cylinder breaks
I was always told 28 days was the magic number and that was that. Then last month a lab tech in Toledo explained that cylinders get broken at 7 and 14 days too, mostly so we can catch bad mixes early instead of waiting a month to find out. I had no idea concrete gets about 70 percent of its design strength by day 7, and that final breaks at 28 days can still vary by a few hundred PSI from cylinder to cylinder. Now I'm sitting here wondering how many pours I signed off on without ever seeing those early breaks. Do you all ask for 7 day results on every job, or only when the mix feels off?